Case Study
Case Study Retail Bangkok
- Sector: Retail Commercial Mall
- Location: Bangkok, Thailand
A major retail complex housing home furnishing, building materials, and design brands. Retrofit delivered under a 15-year Retrofit–Operate–Transfer (ROT) model.
Challenge
Four ageing air-cooled chillers were due for replacement. Rising cooling demand and higher ambient temperatures caused a 4% annual increase in energy use from 2023 to 2024. The upgrade had to be completed without disrupting tenant operations.
Solution
Five new high-efficiency water-cooled chillers installed with advanced monitoring and control systems to optimise load. The ROT model ensured guaranteed performance through integrated operation, maintenance, and continuous energy optimisation.
Outcome
Five new high-efficiency water-cooled chillers installed with advanced monitoring and control systems to optimise load. The ROT model ensured guaranteed performance through integrated operation, maintenance, and continuous energy optimisation.